DRAFT
MINUTES of the
Sweden Fire Station Building Committee (SFSBC) regular meeting on
Present: Members:
Wolfgang Duve, Wayne Miller, Julie McQueen, John P. Smith, Patrick Wood
Public & Guests:
None
Absent: Bill
Morrisseau,
These notes are not necessarily in the order in which
things were discussed. They are
Assignments from the February 12, 2008 Meeting:
·
Wolfgang will generate copies of all 3 building options (1 at 50 X
70, 1 at 62 X 70, and 1 at 64 X 80 with the meeting room moved toward the front
door) on the computer for presentation at the Information Meeting to be held on
·
·
*Julie was finally able to connect with Shawn Bergeron on
Assignments from the January 8, 2008 Meeting:
·
Wolfgang will contact
·
* Wolfgang spoke to
·
Wolfgang will contact the surveyor used in 2005 (Points North from
·
* Wolfgang contacted the surveyor and got a price of $350 to do
the survey again but we do not know if this includes the updated drawing. It
does not include the new or amended deed (cost unknown) or the cost to register
the new deed (about $18).
It is estimated the whole thing will cost less than $1,000.
·
·
* Kevin Drew, VP of L.A. Drew Construction Co. spoke at the
Assignments from the October 23, 2007 Meeting:
·
Julie requested that all members who have recommendations
regarding possible contractors, etc. please verify current names, addresses and
additional contact information and forward them to her. She will compile a list
so the Town is prepared to move forward when it comes time to pursue a cost
estimate.
Assignments from the
·
Ted Harris is to make an inquiry with Maine DOT regarding the
acquisition/storage of excess fill required for site work.
*
We have not received an update on this item as of the
Meeting
Notes:
·
Chairman Wolfgang Duve called the meeting to order at
·
The Committee has been asked to participate in an “Information
Meeting” on
·
John Smith spoke with Lou Bruno in January. His firm would be
unable to stamp any drawings for the Fire Station without being involved in the
construction of the project.; which is completely understandable. It would be
inappropriate for the Committee to commit to anything so this option will be
tabled for the time being.
·
Julie contacted Little Pond Construction and let them know that
the possible arrangement to have Lou Bruno stamp the drawings is off the table
at this time and that the Committee is looking into other options.
·
The Committee appreciates the interest of both Mr. Bruno and
Little Pond Construction in the proposed Fire Station project.
·
The Committee discussed the option of expanding the previously
proposed station to make it 64 ft. wide and 80 ft. long. (5,120 SF)
·
Wolfgang is concerned that if the Town has more than 2 trucks that
are 40 ft. long or more, the 70 ft. length will be inadequate.
·
There were several concerns expressed about doing this:
·
The Committee had discussed equipment that the Town currently
owns, as well as what is anticipated and determined early in the process that
the 70 ft. length would be adequate for their needs for the foreseeable future.
It is unlikely, but not written in
stone that a Town the size of
·
The option approved by the Committee in November was 4,340 SF in
size; which is 16% larger than the current Denmark Station but has a meeting
room of similar size. This newly proposed expansion would increase the size of
the most recent option by an additional 18% and is 37% larger than the Denmark
Station.
·
This will not only add to the cost of construction, but will
increase maintenance (heat, etc.) by as much as well.
·
The Denmark Station is 50 X 70 (3500 SF) + a 240 SF Meeting Room
for a total of 3740 SF. To some, it would be difficult to justify anything much
larger than that for a Town the size of
·
·
The Committee had decided to maintain a 70 foot length in order to
reduce the need to construct a building on fill. The committee has determined
that there is approximately 130 feet of useable space from the front of the Town
Office (which coincides with the front lot line for the Fire Station) before any
significant fill would be required. With the previously proposed station, there
would be a 70 foot apron and a 70 foot building which would require building on
10 foot of fill. Moving the lot line 10 foot forward would reduce the
possibility of having to build on fill. It may be possible to move the lot line
even further forward, but care would have to be taken to be sure that there was
no interference with the abutter’s well before that determination could be
made. It would be important to find this out prior to the March 8th meeting.
·
A station similar to
·
Some members of the Committee visited the Center Conway station on
·
A majority of the
·
The next meeting on
·
At the
·
Option 1 will be the 50 X 70 ft. (3500 SF) option arranged in such
a way that a meeting room could be added at a later date.
·
Option 2 will be the previously submitted option of a 64 X 70
building (4340 SF).
·
Option 3 will be the new, larger version which is 64 X 80 (5120
SF)
·
The Committee will show sketches of these 3 options at the
information meeting the week prior to the Town Meeting.
·
The committee discussed the alternatives for deciding which option
should be further pursued (for which option will the Town pay to have drawings
and specifications developed):
A public hearing could be held
after the Town Meeting, and the option to be pursued could possibly be decided
by a straw vote at that time. This would not be a guarantee that this building
would ultimately be accepted by the Town, but would give the Committee the
direction they need. Enough money would need to be appropriated at the Town
meeting, prior to the public hearing to produce plans and specifications.
An arrangement could be made with
the Selectmen to direct the Committee to pursue whatever option they determined
had the most support.
·
After Plans and Specifications are produced, the project would go
out to bid and the Committee would then have something to present to the Town
for a vote on appropriating or borrowing money to build the project. Again, this
would not be a guarantee that the option pursued by the committee for design
would be approved.
·
The Committee has requested that an article for $10,000 be
included in the warrant for the next Town Meeting. The Committee should be
prepared to answer questions about this article. The $10,000 request was based
on having prices to do the plans and specifications, to have the drawings
stamped and to do the survey. At this time, we do not have the commitment to
stamp the drawings and should be up front about that fact. The Town may
ultimately have to hire an architect; but there should still be an article
presented in order to start a reserve fund for the proposed fire station as part
of the Capital Investment Plan Implementation.
·
The cost of the building will also be an issue. It is important to
acknowledge that at this time the Committee doesn’t know what that cost will
be. It will be determined by the type of building that is pursued, as well as
the options and the contractor that are chosen. The committee has received a
wide range of “ballpark” figures. It would be reasonable to acknowledge that
it looks as if a metal building is more cost effective than a stick built
building. Additional equipment required once the building is complete
(generator, computers, lockers, shelving, furnishings, etc.) should also be
addressed as a part of the cost of the new Fire Station; as well as the cost of
running the station once it is complete (the cost of utilities, will high speed
internet be expected, that sort of thing).
·
It is in the Committee’s best interest to lay it all out on the
table at this point to maintain the trust of the Community.
·
At the next meeting the Committee will prepare for the Information
Meeting presentation.
·
Wolfgang will produce all three options on the computer, and we
will have 8-1/2” X 11” drawings to share at the meeting.
·
The next meeting will be